AVIX VALUE STREAM MAPPING: STEP-BY-STEP

Open AVIX and click on the "Balancing" icon in the top menu.

Skärmbild 2024-12-04 114241.png
Picture 1: Default start layout of Balancing.

Setting Takt Time

Select the Line and fill in the Takt Time. Set Takt Time:

    Enter the Takt Time directly if you know it.

    manuallytakttime.png
    Picture 2: Manual input of Takt Time

      Use the Takt Time Calculator to calculate it.

      takttimecalculator.png
      Picture 3: Click on icon to open Takt Time calculator and calculate Takt Time automatically.

      Setting Parts Per Cycle
        Select the workstation. In the Workstation View, go to the "Cost and VSM" tab. Edit the following fields as needed:
        -Scrap Rate
        - Changeover Time
        - Changeovers Per Day
        - Select information arrows from the dropdown menu:
          - Electronic, Manual, or None (default).
          - Enter the Information Frequency text in the field below.

        partpercycle.png
        Picture 4: Steps for adding produced parts per cycle and information frequency on workstation.

        Adding Buffer/Inventory

        Right click on a workstation, then select "Create" > "Buffer".
        AD_4nXfQlAi1gKh6bKgt2jYjiHV5TMfuTHYPKrhCHYkF7F0K-VXCn_da2iiXg8XAAAvFoIizgVDvqNE4toqXLJeWolplAiR_M4WSTAAs1vZlcLwf1yUyRPtkQrl8zJGZ733207kqnwOZ?key=BKv8agySwZOpenlXpgzvLHKv

        Picture 5: Right click on the workstation to add a buffer.

          In the Buffer View, set the Capacity, which will appear as inventory in the Value Stream Map. Drag and drop the buffer to adjust its position:
          - Default: At the end of the workstation, representing inventory between stations.